National projects
1233projects
₱29.78Bin all
187ongoing
32slow
- Roads and bridges ₱14.88B
- Flood control ₱7.74B
- Buildings ₱5.14B
- Schools ₱1.27B
- Other ₱624.6M
- Water ₱113.7M
Showing 901 to 930 of 1,233
Construction of school buildings in the elementary classrooms jaro ii es, 2sty4cl
Schools · 2018 · G.F. FALCIS CONSTRUCTION & SUPPLY
₱8.9MCompleted · 100%
Construction of multi-purpose building, Brgy. poblacion alimodian
Buildings · 2018 · J'14 CONSTRUCTION & SUPPLY
₱4.9MCompleted · 100%
Rehabilitation of multi-purpose building of pescadores, Dapdap hs, Camangahan es, Namocon es, Cambitu hs, Iloilo 1st
Buildings · 2018 · ALJ CONSTRUCTION AND SUPPLY
₱2.5MCompleted · 100%
Rehabilitation of multi-purpose building of cabasi es, Tabiac es, Igbaras hs, Siwaragan es and san rafael es, Iloilo 1st
Buildings · 2018 · ALJ CONSTRUCTION AND SUPPLY
₱2.5MCompleted · 100%
Iloilo circumferential road 3 incl. row
Roads and bridges · 2018 · A.M. ORETA & CO., INC. / ALLENCON DEVELOPMENT CORPORATION
₱125.5MCompleted · 100%
Panay east - west road (iloilo section)
Roads and bridges · 2018 · A.M. ORETA & CO., INC. / ALLENCON DEVELOPMENT CORPORATION
₱135.6MOn-Going · 79%
Construction of multi-purpose building, Brgy. poblacion zarraga
Buildings · 2018 · ED1SON DEVELOPMENT & CONSTRUCTION INC.
₱4.9MCompleted · 100%
Construction of multi-purpose building (weaving center), Miag-ao
Buildings · 2018 · PITONG BUILDERS & CONSTRUCTION SUPPLY, INC.
₱3.0MCompleted · 100%
Widening iloilo city- leganes-dumangas coastal rd. incl. row-k0003+(-110)-k0003+(-110)
Roads and bridges · 2018 · J E G CONSTRUCTION FIRM CORPORATION
₱2.4MCompleted · 100%
Construction/improvement/rehabilitation/completion of barangay road, Barangay punong, Lapuz
Roads and bridges · 2018 · 5'S CONSTRUCTION & SUPPLY
₱1.9MCompleted · 100%
Rehabilitation/concreting of road, Villa carolina street, Brgy. yulo drive, Arevalo
Roads and bridges · 2018 · G.F. FALCIS CONSTRUCTION & SUPPLY
₱2.4MCompleted · 100%
Concreting of brgy. sambag (san paolo) - jaro-pavia boundary fmr, Brgy. sambag and brgy. jaro
Roads and bridges · 2018 · ALJ CONSTRUCTION AND SUPPLY
₱4.7MCompleted · 100%
Construction of rainwater collection system (rwcs)
Water · 2018 · ALJ CONSTRUCTION AND SUPPLY
₱3.1MCompleted · 100%
Construction of flood mitigation structure - construction of revetment wall at dungon creek section 1 (brgy. dungon a, Jaro - brgy. sta. rosa, Mandurriao)
Flood control · 2018 · IBC INTERNATIONAL BUILDERS CORPORATION
₱41.9MCompleted · 100%
Rehabilitation/concreting of road, Pepita aquino street, Brgy. veterans village, City proper
Roads and bridges · 2018 · H.F. ENTERPRISES
₱3.8MCompleted · 100%
Construction of multi-purpose building (hall), Brgy. hibao-an norte, Mandurriao
Buildings · 2018 · EZ GOLD CONSTRUCTION & SUPPLY
₱2.1MCompleted · 100%
Concreting of brgy. hinactacan fmr, Brgy. hinactacan, La paz
Roads and bridges · 2018 · ALJ CONSTRUCTION AND SUPPLY
₱9.4MCompleted · 100%
Construction of multi-purpose building, Barangay mv hechanova
Buildings · 2018 · ALJ CONSTRUCTION AND SUPPLY
₱975KCompleted · 100%
Construction of multi-purpose building, Iloilo national high school, La paz
Schools · 2018 · JHALL MARKETING & SERVICES
₱2.0MCompleted · 100%
Construction of 4-classroom alameda national high school (makeshift building), Brgy. alameda igbaras
Schools · 2018 · PITONG BUILDERS & CONSTRUCTION SUPPLY, INC.
₱2.0MCompleted · 100%
Construction of rainwater collection system (rwcs) in region vi
Water · 2018 · S.T. SALCEDO CONSTRUCTION CORP.
₱3.2MCompleted · 100%
Construction of jnr aripdip - bagacay jnr road, San rafael - lemery
Roads and bridges · 2018 · WOODLAND CONSTRUCTION & SUPPLY, INC.
₱94.4MCompleted · 100%
Widening-rizal-jordan wharf rd incl. row-k0008+(-408)-k0008+565
Roads and bridges · 2018 · S.T. SALCEDO CONSTRUCTION CORP.
₱39.3MCompleted · 100%
Widening-guimaras circumferential rd incl. row-k0006+600-k0006+789, K0007+151-k0007+237, K0007+354-k0008+000
Roads and bridges · 2018 · S.T. SALCEDO CONSTRUCTION CORP.
₱37.5MCompleted · 100%
Widening of bridge - monfort vigilar bridge (b00184pn) along iloilo east coast capiz road, Brgy. tabucan, Btac. nuevo
Roads and bridges · 2018 · GOOD FORTUNE INTERNATIONAL, INC.
₱16.9MCompleted · 100%
Concreting of sitio bungao, Brgy. amparo, Municipality of pavia to zone 1, Brgy. palagon, Municipality of sta. barbara
Roads and bridges · 2018 · A.D. PENDON CONSTRUCTION & SUPPLY, INC.
₱9.4MCompleted · 100%
Widening-guimaras circumferential rd incl. row - k0008+000-k0009+578
Roads and bridges · 2018 · S.T. SALCEDO CONSTRUCTION CORP.
₱60.6MCompleted · 100%
Rehabilitation of multi-purpose building, Municipality of badiangan
Buildings · 2018 · H.F. ENTERPRISES
₱3.8MCompleted · 100%
Construction (completion) of multi-purpose building of the municipality of lambunao
Buildings · 2018 · PESOM CONSTRUCTION SERVICES
₱9.6MCompleted · 100%
Widening of bridge - jct. tabucan - cabatuan - consolacion - san miguel leading to iloilo international airport (morobwan bridge widening)
Roads and bridges · 2018 · SBF CONSTRUCTION & DEVELOPMENT CORPORATION
₱13.7MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
A.D. PENDON CONSTRUCTION & SUPPLY, INC.70 projects · ₱3.19B
2
IBC INTERNATIONAL BUILDERS CORPORATION64 projects · ₱5.29B
3
5'S CONSTRUCTION & SUPPLY61 projects · ₱364.3M
4
S.T. SALCEDO CONSTRUCTION CORP.58 projects · ₱886.3M
5
G.F. FALCIS CONSTRUCTION & SUPPLY42 projects · ₱303.2M