National projects
984projects
₱50.74Bin all
148ongoing
24slow
- Buildings ₱26.04B
- Flood control ₱14.06B
- Roads and bridges ₱8.12B
- Other ₱1.60B
- Schools ₱917.2M
Showing 31 to 60 of 984
Construction of multi-purpose building, Barangay lower bicutan, Taguig city (phase 4)
Buildings · 2025 · ELITE GENERAL CONTRACTOR AND DEVELOPMENT CORP. / ZYRE TRADING AND CONSTRUCTION
₱7.2MTerminated · 100%
Construction (completion) of multi-purpose building b along laguna lake highway (c6 road), Barangay lower bicutan & barangay hagonoy
Buildings · 2025 · RGDG CONSTRUCTION
₱48.5MOn-Going · 0%
Construction of multi-purpose building, National language skills center, Tesda complex
Buildings · 2025 · C.T. LEONCIO CONSTRUCTION & TRADING
₱97.1MOn-Going · 15%
Construction (completion) of multi-purpose building at purok 10, Barangay south daang hari
Buildings · 2025 · C.L. MORALES CONSTRUCTION AND TRADING
₱9.7MOn-Going · 0%
Construction of ten (10) storey multi purpose army transient facility, Fort andres bonifacio, Phase iii
Buildings · 2025 · AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129) / DOUBLE 12 CONSTRUCTION & SUPPLY
₱0Terminated · 0%
Retrofitting/strengthening of permanent bridges - nichols field br. (b01805lz) along nichols field rd.
Roads and bridges · 2025 · LE BRON CONSTRUCTION
₱95.4MOn-Going · 31%
Retrofitting/strengthening of permanent bridges - nichols field interchange br. (b01813lz) along nichols field rd.
Roads and bridges · 2025 · LE BRON CONSTRUCTION
₱95.5MOn-Going · 50%
Construction of drainage at green village/camp bagong diwa, Barangay lower bicutan
Flood control · 2025 · ZYRE TRADING AND CONSTRUCTION
₱23.0MOn-Going · 100%
Construction of a multi-purpose building with site development, Brgy. central bicutan
Buildings · 2025 · C.S. GARCIA CONSTRUCTION CORPORATION
₱48.5MOn-Going · 32%
Construction (completion) of multi-purpose building, Including site development at tcu, Barangay central bicutan
Buildings · 2025 · NEWBIG FOUR J CONSTRUCTION INC.
₱48.5MOn-Going · 72%
Construction of multi-purpose building, Barangay central bicutan, Taguig city (phase 3)
Buildings · 2025 · C.S. GARCIA CONSTRUCTION CORPORATION
₱48.5MOn-Going · 32%
Construction of multi-purpose building and site development at tcu compound, Barangay central bicutan, Taguig city (phase 3)
Buildings · 2025 · NEWBIG FOUR J CONSTRUCTION INC.
₱48.5MOn-Going · 84%
Rehabilitation of multi-purpose building, Barangay sun valley parañaque city, Metro manila
Buildings · 2025 · GOLDEN 3T CONSTRUCTION CORPORATION
₱9.8MCompleted · 100%
Rehabilitation of t. rayos st., Barangay ligid
Other · 2025 · GR FEVIDAL CONSTRUCTION DEVELOPERS CORPORATION
₱0Terminated · 0%
Construction of multi-purpose facility, Barangay lower bicutan, Taguig city (phase 1)
Buildings · 2025 · A.M. ORETA & CO., INC.
₱145.0MOn-Going · 0%
Rehabilitation of road at barangay wawa
Roads and bridges · 2025 · DAHL CONSTRUCTION CORP.
₱9.4MCompleted · 100%
Rehabilitation of road and alley at barangay bambang
Roads and bridges · 2025 · B. VALENCERINA TRADING & CONSTRUCTION
₱9.4MCompleted · 100%
Construction of slope protection structure along labasan river (west bank), Phase 2, Package 7
Flood control · 2025 · DAHL CONSTRUCTION CORP.
₱93.6MOn-Going · 100%
Construction of multi-purpose building (dormitory), Pup taguig campus - polytechnic university of the philippines
Buildings · 2024 · JUSTBILT BUILDERS
₱39.0MOn-Going · 78%
Rehabilitation of road within the dost bicutan compound
Roads and bridges · 2025 · CHAINWORKS CORP.
₱6.3MOn-Going · 100%
Construction of slope protection structure along taguig river lakeshore area (phase 2)
Flood control · 2025 · RVDP CONSTRUCTION / ZYRE TRADING AND CONSTRUCTION
₱93.8MOn-Going · 100%
Construction of slope protection structure along c-6 open channel (phase 12)
Flood control · 2025 · BLISSFUL CONSTRUCTION INCORPORATED / TUCHAR CONSTRUCTION CORP.
₱93.8MCompleted · 100%
Rehabilitation of road network at barangay new lower bicutan
Roads and bridges · 2025 · DAHL CONSTRUCTION CORP.
₱47.5MOn-Going · 0%
Construction of taguig general hospital (phase 13)
Buildings · 2025 · THAISON BUILDER AND DEVELOPER INC.
₱72.0MCompleted · 100%
Construction of taguig general hospital (phase 12)
Buildings · 2025 · THAISON BUILDER AND DEVELOPER INC.
₱96.0MCompleted · 100%
Convergence and special support program-sustainable infrastructure projects alleviating gaps (sipag)-access roads and/or bridges from the nat'l. road/s leading to major strategic public buildings- facilities- impv't. of road & drainage system along manila
Flood control · 2025 · ANORE CONSTRUCTION
₱95.4MOn-Going · 83%
Preventive maintenance-tertiary roads-south super h-way west service rd-k0011+(-384)-k0012+544
Roads and bridges · 2025 · ALE BUILDERS CONSTRUCTION AND DEVELOPMENT CORP.
₱121.1MCompleted · 100%
Construction of five (5) storey southern police district, Spd quartering facility, Phase iii
Buildings · 2025 · 10-02 ENTERPRISES CO. INC.
₱9.5MOn-Going · 0%
Preventive maintenance - tertiary roads - south super h-way west service rd-k0017 + 000 - k0018 + 370 parañaque city, Metro manila
Roads and bridges · 2025 · GOLDEN 3T CONSTRUCTION CORPORATION
₱26.9MCompleted · 100%
Construction (completion) of taguig national high school
Schools · 2025 · RVDP CONSTRUCTION / ZYRE TRADING AND CONSTRUCTION
₱63.9MOn-Going · 0%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
HONY TRADING & CONSTRUCTION61 projects · ₱1.49B
2
DAHL CONSTRUCTION CORP.52 projects · ₱2.68B
3
FRANZCOR TRADING & CONSTRUCTION52 projects · ₱946.8M
4
B. VALENCERINA TRADING & CONSTRUCTION36 projects · ₱317.9M
5
TUCHAR CONSTRUCTION CORP.29 projects · ₱764.1M